Customer-Provided Utilities Clause
"The Customer shall provide and maintain the electrical and water services identified in Schedule B at the designated connection points before the agreed mobilization date."
What Is a Customer-Provided Utilities Clause?
A Customer-Provided Utilities Clause explains which electricity, water, drainage, lighting, compressed air, network connectivity, or other site utilities a customer must make available to a contractor. It identifies minimum service conditions, connection points, permitted uses, access hours, safety responsibilities, and remedies when the promised supply is unavailable. Construction, equipment installation, manufacturing maintenance, and facility-service contracts use this provision to separate owner-furnished infrastructure from the supplier’s labor and equipment obligations.
Standard Customer-Provided Utilities Clause — Sample Contract Language
A packaging manufacturer hires an installer for a new conveyor. The contract requires three-phase power and compressed air at the installation bay, verified two business days before startup. During testing, pressure repeatedly drops below the agreed range. The installer logs the readings, pauses affected tests, and moves to software configuration while the plant repairs the supply. A documented change request addresses only proven additional commissioning costs.
Why a Customer-Provided Utilities Clause Matters
Project schedules depend on more than labor availability
A qualified technician may arrive with the right parts yet be unable to commission a machine because electrical capacity is insufficient. The clause should make utility readiness an actual project dependency, with measurable parameters and a process for documenting interruptions. Otherwise, each side may blame the other for an idle crew, repeat mobilization, or missed milestone.
Safety duties require separate treatment
A promise to supply power does not authorize unsafe electrical work. On construction sites, applicable occupational safety standards may govern grounding, protective devices, and work near energized circuits. The contract should identify a competent site contact, approved connection method, lockout coordination, and who may isolate equipment. Even when a customer furnishes the source, employers and contractors retain duties imposed by applicable safety law. Contract language cannot transfer away those statutory obligations.
Unmetered consumption can become an unexpected cost
Some projects consume substantial water or electricity during testing, curing, cleaning, or overnight operation. Without a cost-allocation rule, a customer might discover a large utility bill and a supplier might receive an unsupported backcharge. The parties can agree that ordinary consumption is included while exceptional consumption requires notice, metering, or separate approval. Define baselines and measurement methods before a disagreement develops.
How a Customer-Provided Utilities Clause Works
List the utility and technical requirements
An exhibit should identify each promised utility, supply location, voltage, amperage, phase, pressure, flow, temperature, water quality, bandwidth, or other operating criterion. Avoid the vague phrase “utilities as needed.” State whether permanent outlets or temporary distribution are supplied and who provides cables, hoses, transformers, adaptors, and protective devices. DrawingsPatent ApplicationA Patent Application is a filing asking the USPTO to examine an invention for patent protection. Provisional and nonprovisional applications differ in purpose, requirements, examination, timing, publication, and their relationship to later patent...View definition and equipment specifications should match the contractual table. A commissioning plan should identify the test loads and planned duration.
Establish a readiness confirmation process
Require the customer to provide the designated supplies by an agreed lead date and let the contractor inspect or test them before mobilizing. The supplier must promptly report defects it reasonably discovers. If readings are contested, the parties may use a qualified independent tester. A signed readiness form should not excuse a hidden safety defect discovered later.
Separate normal use from interruptions
Define planned outages, emergency shutdowns, maintenance windows, and force majeureForce MajeureForce Majeure is a contract concept that can excuse or delay performance after extraordinary events covered by the agreement. Relief depends on clause wording, causation, notice, mitigation, exclusions, governing law, and the specific...View definition procedures. When supply fails, the contractor should stop unsafe work, protect materials, notify the site representative, and document affected personnel and equipment. The clause can offerOffer and AcceptanceOffer and Acceptance describes how parties manifest mutual assent to a contract. A valid offer gives another party power to accept, while acceptance must objectively communicate assent through an authorized method, subject to...View definition schedule relief for demonstrated critical-path impacts, with extra compensation limited to reasonable, supported costs. State whether the supplier must mitigate by resequencing tasks or bringing temporary equipment, and who approves that alternative.
Control extraordinary utility charges
The parties may include ordinary consumption in the contract price while using meters or agreed rates for high-load testing. Name the party responsible for rental generators, fuel, wastewater handling, temporary distribution, permits, and restoration of disturbed connections. A contractor should not bill for avoidable idle time caused by its own planning failure. Likewise, a customer should not assume free temporary power includes an unlimited industrial test load.
Coordinate access and shutdown authority
Utilities may pass through tenant space, controlled plant rooms, or live production lines. Only authorized personnel should energize or disconnect a circuit. In multi-contractor locations, assign a coordinator for shared loads and outage notices. An agreed procedure also helps distinguish an actual utility failure from a supplier’s failure to request access in time.
Practical Business Examples
Factory equipment commissioning
A packaging manufacturer hires an installer for a new conveyor. The contract requires three-phase power and compressed air at the installation bay, verified two business days before startup. During testing, pressure repeatedly drops below the agreed range. The installer logs the readings, pauses affected tests, and moves to software configuration while the plant repairs the supply. A documented change request addresses only proven additional commissioning costs.
Commercial cleaning at a new property
A facility operator contracts for floor restoration before tenants arrive. When the drain is not available, the cleaner cannot safely dischargeBankruptcy CourtBankruptcy court is the specialized federal court handling bankruptcy cases and related proceedings referred by U.S. district courts. Federal courts have exclusive jurisdiction over bankruptcy cases, including liquidation, repayment, reorganization, claims, automatic-stay disputes,...View definition process water. Both parties approve a lawful containment and removalState CourtA state court is a court established under a state constitution and state law. State courts hear the vast majority of U.S. civil and criminal cases, and their structures, names, procedural rules, and...View definition method with a stated price cap. The project records the change rather than treating an informal site conversation as unlimited authorization.
Variations and Negotiating Tips
For customers and property operators
Limit your promise to identified services and specified connection points. Reserve planned shutdown windows, but give adequate notice where practicable. Ask the contractor to demonstrate mitigation and link compensation to records. Avoid a broad clause stating that every missing utility automatically extends all project deadlines.
For contractors and suppliers
Request measurable capacities, site drawings, verified access, and a named decision-maker. Seek relief for genuine loss of critical-path time and additional approved standby or remobilization expense. Reject clauses that require you to use unsafe power or absorb defects in infrastructure outside your control. Explain what temporary utilities you can provide and at what agreed rates.
Alternatives for short-duration service work
A two-hour technician visit may need only a standard outlet and safe workspace, so a simplified checklist can be sufficient. Large industrial projects may require a technical exhibit, load study, meter log, and outage coordination plan. The right document should reflect the actual consequences of failure, rather than importing detailed power-plant language into a small office installation.
Common Drafting Mistakes
Describing utilities without measurable capacities
“Customer will supply power” leaves unanswered whether the outlet can handle the equipment’s actual load. Attach voltage, capacity, distance, and readiness criteria. Similarly, “water available” does not establish pressure, quality, or lawful discharge arrangements.
Automatically charging all downtime to the customer
A power failure might affect only one workstream. If the contractor could complete other scheduled tasks, charging its entire crew as idle may be unreasonable. Require daily records, mitigation, causationBreach of DutyA breach of duty occurs when a person or entity fails to meet a legal duty owed to another person. In negligence cases, breach is usually one element alongside duty, causation, and damages,...View definition , and an agreed rate or change-order process. Preserve the treatment of concurrent delays under the broader agreement.
Ignoring safety or environmental rules
Customers sometimes promise access to existing panels or drains without confirming that a connection is authorized. The clause should require safe methods, qualified people, and compliance with applicable electrical, wastewater, and site rules. Private allocation of utility costs cannot override a mandatory permit or worker-protection requirement.
Authoritative References and Drafting Checklist
- Identify each owner-furnished utility, connection location, and minimum technical capacity.
- State who provides distribution equipment, temporary fixtures, consumables, and testing instruments.
- Set readiness dates, testing methods, and written signoff responsibilities.
- Coordinate shutdown notices, access windows, safe isolation, and emergency contacts.
- Define permitted consumption, metering, extraordinary charges, and waste handling.
- Require prompt interruption records, mitigation, and approved alternative services.
- Align schedule relief and pricing with change orders, delay clauses, and governing lawBoilerplate ClauseA boilerplate clause is standardized contract language addressing recurring legal mechanics such as notice, assignment, governing law, waiver, severability, and integration.View definition .
Authoritative references: OSHA Construction Electrical Wiring Design and Protection; OSHA General Electrical Work Protections. These references provide context, not a substitute for checking the law, contract terms, and standards that actually govern the project.
Related LawyerAI Glossary Terms
Explore connected topics in the LawyerAI glossary: Customer Site Access Delay Clause, Service Level Downtime Exclusion Clause, Force Majeure. Read related provisions together so evidence duties, review deadlines, payment triggers, and remedies stay consistent throughout the agreement.
Frequently Asked Questions
Must a customer provide free electricity to a contractor?
Only if the contract or another applicable obligation requires it. Many service arrangements assume normal access to site power, but the scope and charges should be express. The customer may include a reasonable allowance, provide metered use, or require the supplier to bring its own source. A defined connection point matters as much as the price.
Can a contractor stop work when site power is unsafe?
A contractor should not perform work that exposes workers to an unsafe electrical condition. Applicable safety duties may require protective steps regardless of the contract’s commercial remedies. The parties should establish a stop-work and escalation process that allows the condition to be assessed, recorded, and corrected before affected activities resume.
Who pays for a temporary generator after an outage?
That depends on the allocation of utility responsibility, reason for the outage, authorization process, and applicable law. A contract may make the customer pay reasonable approved generator costs after a customer-caused interruption. It may instead place contingency power within a supplier’s fixed price. Document the proposed rental, fuel, connection, and safety arrangements before use.
Does an outage automatically extend the completion date?
Not necessarily. Many clauses require notice and a demonstrated effect on scheduled work. The parties should examine critical-path delay, alternative tasks, concurrency, and mitigation. An interruption that causes no meaningful delay may support no extension. Keep records of actual dates rather than assuming every outage adds the same number of days.
What if the customer cannot provide the specified water quality?
The contractor should document the variance and explain which tasks or equipment it affects. The parties can agree on filtration, an alternative water source, postponed testing, or a revised process. Any cost or warrantyWarrantyA warranty is an express or implied assurance concerning goods, services, property, or performance and can create contractual remedies when breached.View definition consequences should be confirmed in writing. Environmental discharge duties and equipment manufacturer limits still require separate attention.
Key Takeaway
A Customer-Provided Utilities Clause turns a vague site-support promise into measurable supply requirements, readiness checks, safety procedures, and fair cost allocation. It works best when the technical exhibit, schedule, change-order process, and site rules all describe the same practical obligations.