Tentative Daily Extra Work Agreement Template Site Costs

  • Typical length: 4–6 pages
  • AI Assisted
  • Export: PDF & DOCX
  • Multi-jurisdiction ready

Create your custom agreement in minutes!

  • Downloaded 9 times
Tentative Daily Extra Work Agreement Template Site Costs preview
On this page
  1. Who can use this daily extra work agreement?
  2. Know the difference between a field record and a change order
  3. Describe the original scope and the changed condition
  4. Identify who requested or directed the work
  5. Create a daily labor log with accurate classifications
  6. Track equipment, rentals, and standby time separately
  7. Document materials with quantities and receipts
  8. Set the pricing basis without pretending it is final
  9. Address schedule impact and delay documentation
  10. Use photos, measurements, and contemporaneous evidence
  11. Clarify what each signature acknowledges
  12. Handle urgent work and verbal instructions thoughtfully
  13. Reconcile daily tickets into the final adjustment
  14. Review lien, payment, and public contracting limits
  15. How to prepare a daily extra work agreement step by step
  16. Practical example
  17. Common mistakes to avoid
  18. Final review checklist
  19. Frequently asked questions
  20. Official sources and further reading

Tentative Daily Extra Work Agreement Template Site Costs

Quick answer: A daily extra work agreement records work outside or potentially outside the original construction scope, including who requested it, what changed, labor hours, materials, equipment, and a method for reviewing costs. It is useful when final pricing has not been agreed, but the project must move forward. The parent contract determines who may authorize a change, whether notice is required, and whether a daily signature approves quantities, price, or neither.

A crew discovers deteriorated piping behind a wall and is told to perform replacement work so the schedule can continue. The supervisor wants the costs recorded, but the owner has not approved a final price. A daily extra work form gives both sides a contemporaneous record of activities and resources. The document must separate acknowledgment of field quantities from contractual authorization, or a seemingly routine signature may create a dispute. This guide explains how to capture each day’s information, handle disputed pricing, and connect field tickets to formal change orders.

Who can use this daily extra work agreement?

General contractors, subcontractors, construction managers, owners representatives, field engineers, estimators, and public project teams may use this form to organize potential extra work. It is especially useful for unexpected site conditions, emergency stabilization, directed overtime, additional excavation, or redesign-related tasks. Before relying on any agreement, read the prime contract, subcontract, project specifications, approved change procedures, and any public procurement rules that apply.

Standard Tentative Daily Extra Work Agreement Template Site Costs — Sample Contract Language

During excavation, a contractor finds an undocumented buried utility. The authorized project representative directs a limited reroute while an engineer reviews the design. The foreman logs two operators, a mini excavator, replacement fittings, and measured excavation quantities on a dated ticket. The field representative signs only to acknowledge observed hours and quantities. The contractor separately submits pricing and a request for schedule relief under the change clause. The ticket supports review but is not treated as automatic approval of every dollar.

Know the difference between a field record and a change order

A daily extra work ticket documents what happened at the site. A change order typically modifies the contract scope, price, or time under the governing agreement. A construction change directive may instruct work to proceed while the financial adjustment remains unresolved. The names and legal effects differ by contract; never assume that every signed ticket automatically increases the contract sum.

The AIA describes change orders and change directives as distinct documents in its commonly used contract system. Your project may use different forms or conditions. Read the change management article in the actual agreement to understand who must sign, what counts as notice, and whether the field representative has authority to approve costs.

Describe the original scope and the changed condition

Identify the contract, project address, building or area, relevant drawing or specification, and the original task. Then explain what differed from expected conditions. A short note like “extra plumbing” is insufficient when the project later needs to determine whether the work was included in the base bid. Record the date the condition was discovered and who observed it.

Attach a drawing revision, photo, request for information, site instruction, or correspondence that supports the change. Record exact quantities when feasible, such as linear feet of pipe, cubic yards of excavation, or number of fittings. Distinguish an estimate from verified measured quantities to avoid turning a tentative document into an inaccurate final claim.

Identify who requested or directed the work

Write the full name, employer, title, and contact information of the person who directed the work. Note whether instruction was verbal, written, issued through a project platform, or reflected in a formal directive. Different participants may have authority to confirm work occurred but not to approve a price. Make that distinction visible on the signature lines.

If an instruction comes from someone outside the contract’s approval chain, notify the authorized person promptly. A superintendent may confirm that workers were present while the owner or contracting officer retains authority to modify the contract. Do not rely on the appearance of a signature alone to resolve that allocation of authority.

Create a daily labor log with accurate classifications

For each worker or trade, list role, work date, start and stop time, regular hours, overtime hours, and specific extra work activity. Keep base contract tasks separate if the same crew performed both on a single day. If labor rates are relevant, include the contractual rate schedule or a reference to it rather than improvising a new rate after the fact.

Record foreman time, travel, supervision, and overtime only when permitted by the agreement. The same individual should not be billed for overlapping hours on multiple change tickets. Payroll records and certified wage requirements may differ on public projects; maintain the source records needed to support the amounts ultimately claimed.

Track equipment, rentals, and standby time separately

List machinery by equipment type or identifier, hours operated, hours on standby, applicable rates, and why the equipment was required for the extra work. Owned equipment and rented equipment may have different allowed billing methods. If the form includes fuel, delivery charges, attachments, or operator time, check whether those costs are already included in an agreed equipment rate.

Standby charges are frequently disputed. Note the reason an item could not be used elsewhere and whether the delay arose from the directed change. Preserve rental tickets and equipment logs. A daily quantity acknowledgment should not by itself settle whether every claimed standby cost is recoverable under the contract.

Document materials with quantities and receipts

Record material description, part number if useful, unit, quantity delivered, quantity used, unit price, and any approved markup. Keep supplier invoices, delivery tickets, and return credits. Differentiate materials consumed in the extra work from items purchased but unused. Where a substitution was necessary, note why and who approved it.

Record waste, freight, storage, and taxes only as permitted by the relevant contract. For emergency purchases, attach the authorization and explain the purchasing constraint. Contractors and owners both benefit from transparent costs rather than lumping labor, equipment, and materials into a single unsupported number.

Set the pricing basis without pretending it is final

The form may use time and materials, agreed unit prices, negotiated lump sum, or another approach specified in the contract. If final cost is unsettled, state the interim accounting method and mark amounts as estimates where appropriate. Identify labor burdens, overhead, profit, subcontractor markups, and limits only when authorized. An omitted markup can cause conflict just as easily as an unauthorized one.

For a tentative daily form, use a clear reservation such as “quantities verified; entitlement and price subject to contract review” if that matches the parties’ intent. Do not insert language that contradicts a signed master agreement. Change requests should be reconciled later through the document required by that agreement.

Address schedule impact and delay documentation

Extra work can affect critical activities without necessarily entitling the contractor to additional calendar days. Record whether the work disrupted an existing sequence, required overtime, or delayed successor activities. Include the current schedule activity identifier where one exists, and state whether a separate time impact analysis will be submitted.

Avoid automatically adding one day to the project completion date for each day of extra work. Parallel tasks, float, mitigation measures, and contract notice provisions matter. Explain who must approve an extension and when the request must be submitted. Preserve daily progress reports and updated schedules that may support later review.

Use photos, measurements, and contemporaneous evidence

Site photos should show the work location, relevant condition, and scale when possible. Date and label them so reviewers can connect them to a particular daily form. Measurements, inspection reports, material tickets, and equipment logs are most useful when completed promptly while the facts are still fresh. Save the original files rather than only compressed screenshots.

A photograph does not replace a required written change directive. Likewise, an unsigned ticket may still document facts without establishing price approval. Keep source evidence and contractual authorization as separate categories in the project file, and record when a later revision corrects a previously reported measurement.

Clarify what each signature acknowledges

Include signature blocks for the preparing contractor and the reviewing owner or construction manager, with printed name, title, date, and time. Add a field identifying whether the reviewer acknowledges quantities only, verifies work was performed, or has authority to accept the stated price. Leave space for disputed entries and written explanations.

Some projects require daily signatures to document time and materials, while expressly reserving review of entitlement. Others impose a stricter preapproval requirement. A signature without clear scope can create conflicting expectations. Make the approval language consistent with the prime contract, subcontract, and written project change procedures.

Handle urgent work and verbal instructions thoughtfully

A safety hazard or exposed utility can require rapid action, but urgency does not always eliminate notice requirements. Record who identified the hazard, what protective measures were necessary, and when the contracting parties were contacted. Use the project’s emergency protocol and confirm verbal instructions in writing as soon as practical.

On a public contract, only authorized personnel may issue particular modifications; federal acquisition rules prescribe formal change processes. Private projects differ, but authority still matters. Avoid assuming that the presence of an inspector or owner’s employee gives that person power to commit extra project funds.

Reconcile daily tickets into the final adjustment

Number tickets consistently and tie each to a change request, directive, or potential change order. At an agreed interval, summarize labor, materials, equipment, subcontractor costs, credit adjustments, and any pending disputed items. Compare supporting records to invoices and note what has already been paid through progress billing.

Once pricing and schedule effects are agreed, use the contract’s required change order or supplemental agreement. Do not double count a cost that was already included in base work or another approved change. Preserve the final reconciliation alongside the original daily records so a reviewer can understand how tentative estimates became final values.

Review lien, payment, and public contracting limits

The right to payment may depend on strict notice, change authorization, prompt payment, lien, and public procurement requirements. A well kept time and materials ticket is helpful evidence, but it may not satisfy a contract’s written order requirement or a statutory notice deadline. Subcontractors should also review obligations in their own subcontract rather than relying only on the prime contractor’s procedures.

Public work may include special cost accounting and wage documentation obligations. Review these with counsel or the contracting officer where appropriate. Avoid threatening a lien or stopping work without first understanding the governing contract, payment status, and legal process.

How to prepare a daily extra work agreement step by step

Work through these steps with the underlying records nearby. Confirm which contract provisions and local legal requirements actually apply to the situation.

  1. Verify change procedures: Read contract clauses describing authorized directives, written notice, pricing, and time extensions.
  2. Open a numbered daily record: Identify the project, contract, location, day, and the specific extra work request.
  3. Describe work performed: Distinguish original scope from changed work and record measurements, causes, and evidence.
  4. Log labor and equipment: Record names or classifications, hours, tasks, equipment use, and supporting records.
  5. Capture materials and purchases: Include quantities, receipts, delivery tickets, approved rates, and returns.
  6. Note authority and reservations: Identify who instructed work and clarify whether signatures verify facts or approve price.
  7. Track time effects: Record schedule impacts and flag any separate formal extension request.
  8. Reconcile and close: Combine tickets into a documented change proposal and obtain the required final authorization.

Practical example

During excavation, a contractor finds an undocumented buried utility. The authorized project representative directs a limited reroute while an engineer reviews the design. The foreman logs two operators, a mini excavator, replacement fittings, and measured excavation quantities on a dated ticket. The field representative signs only to acknowledge observed hours and quantities. The contractor separately submits pricing and a request for schedule relief under the change clause. The ticket supports review but is not treated as automatic approval of every dollar.

Common mistakes to avoid

Common errors include combining base and extra work on the same labor hours, failing to identify the official directive, counting standby equipment twice, omitting receipts, and treating a field signature as universal price approval. Another mistake is recording a schedule delay without linking it to the actual affected activity. Maintain clear cost and authority records from day one.

Final review checklist

  • Contract change procedure reviewed.
  • Project and ticket numbers assigned.
  • Original scope and changed work distinguished.
  • Authorized direction documented.
  • Labor hours and classifications recorded.
  • Equipment time and rates supported.
  • Material quantities and invoices preserved.
  • Schedule effects identified.
  • Signature meaning and reservations stated.
  • Final change reconciliation process assigned.

Frequently asked questions

What is a daily extra work agreement?

It records extra or disputed construction work performed on a particular day, including instructions, labor, materials, equipment, and review of quantities.

Is a signed daily work ticket the same as a change order?

Not necessarily. The governing contract determines whether signatures confirm quantities, authorize work, or approve a price change.

Can contractors charge time and materials for extra work?

Sometimes. The contract or authorized directive must permit the method and may define allowable labor, material, equipment, and markup costs.

What should a daily extra work record include?

Include the project, work description, dates, instructions, labor, equipment, materials, photos, cost basis, and reviewer acknowledgments.

What if the owner disputes the added costs?

Preserve supporting records, follow the contract dispute procedure, and distinguish factual quantity verification from entitlement and rate approval.

Does extra work automatically extend the completion date?

No. Contract notice requirements, schedule impact, and formal approval determine whether an extension is warranted.

Official sources and further reading

These sources provide additional legal or procedural context. Check the current text and local rules before acting. The organizations linked below do not endorse this template.

Important notice: Change authority, public procurement rules, notice requirements, and payment remedies are contract and jurisdiction specific. A daily record does not independently authorize a contract modification. This article is general educational information, not individualized legal advice. Consult a qualified professional when important rights are involved.

Get your complete legal document in minutes

  1. Step 1

    Select a template

    Start with a ready-made legal template built for common real-world needs.

  2. Step 2

    Add your details

    Fill in the key facts and tailor the document to your situation.

  3. Step 3

    Review & export

    Check the finished document, make edits if needed, then download or export it.

Tentative Daily Extra Work Agreement Template Site Costs FAQs

What is a daily extra work agreement?

It records extra or disputed construction work performed on a particular day, including instructions, labor, materials, equipment, and review of quantities.

Is a signed daily work ticket the same as a change order?

Not necessarily. The governing contract determines whether signatures confirm quantities, authorize work, or approve a price change.

Can contractors charge time and materials for extra work?

Sometimes. The contract or authorized directive must permit the method and may define allowable labor, material, equipment, and markup costs.

What should a daily extra work record include?

Include the project, work description, dates, instructions, labor, equipment, materials, photos, cost basis, and reviewer acknowledgments.

What if the owner disputes the added costs?

Preserve supporting records, follow the contract dispute procedure, and distinguish factual quantity verification from entitlement and rate approval.

Does extra work automatically extend the completion date?

No. Contract notice requirements, schedule impact, and formal approval determine whether an extension is warranted.