Change Order
"The contractor submitted a change order for extra electrical work, including a revised price and a five-day extension to the construction schedule."
What Is a Change Order?
A change orderMaster Service Agreement (MSA)A Master Service Agreement, or MSA, sets recurring legal and commercial terms for an ongoing service relationship. The parties can then use SOWs, order forms, or schedules for project-specific scope, pricing, deliverables, and...View definition is a document that records an agreed modification to the scope, price, schedule, or other project requirements under an existing contract. It is especially common in construction, although similar change-control documents are used in technology, consulting, design, and other project-based services.
For example, a building owner may request an additional electrical circuit after work begins. A signed change order can describe the new task, revised cost, and effect on the completion date.
Standard Change Order — Sample Contract Language
Illustrative language only: "Change Order No. 04 modifies the Work under the Agreement dated March 1. Contractor will install two additional data outlets as described in Exhibit A. The Contract Price increases by $1,200, and the Substantial Completion Date extends by two calendar days. All other terms remain unchanged."
Why Are Change Orders Used?
Projects evolve. New information may reveal site conditions, technical constraints, or stakeholderInterpleaderInterpleader allows a stakeholder facing competing claims to the same property or obligation to bring the claimants into one action and reduce the risk of multiple liability.View definition requests that were not included in the original scope. A change order gives the parties a structured way to assess the effect of those changes before work proceeds.
Without written approval, the customer may view extra work as included in the original fee, while the provider may expect additional payment. The document helps record the shared decision.
What Typically Triggers a Change Order?
Common triggers include owner-requested additions, changed specifications, unforeseen conditions, required design revisions, substitutions, and schedule adjustments. In software projects, a request for new integrations or functionality may serve the same practical purpose.
Not every difference requires a formal change order. Check the contract for the distinction between included revisions, administrative instructions, and changes that affect compensation or time.
What Should a Change Order Include?
A useful form identifies the project, existing agreement, change number, description of new or removed work, amount added or deducted, schedule effect, supporting exhibits, and required approvals. It should also record the new total contract amount when that calculation is relevant.
For construction, the AIA G701 change order description identifies scope, contract sum, and contract time as key elements in the documented agreement.
What Is the Difference Between a Change Order and a Change Request?
A change request is usually a proposal to alter the work. A change order generally records a modification that has received the approvals required by the underlying contract. The labels can vary across organizations and industries.
A request may be rejected, revised, or accepted. Do not assume that submitting a priced proposal automatically authorizes the additional work.
How Does a Change Order Affect Project Price?
A change may increase the contract amount, reduce it, or leave it unchanged. The pricing could use a fixed agreed sum, specified unit prices, time and materials, or another method permitted by the contract.
Break out labor, materials, equipment, subcontractor costs, and any agreed markup when they matter. Check whether the amount also includes taxes, contingencies, or related work that would otherwise be billed separately.
How Does a Change Order Affect Deadlines?
Extra work does not always justify a schedule extension, and even a small task may affect a critical dependency. A change order should explicitly identify the number of added or reduced days and the revised completion date when applicable.
For a software launch, explain whether a new feature delays testing or customer acceptanceOffer and AcceptanceOffer and Acceptance describes how parties manifest mutual assent to a contract. A valid offer gives another party power to accept, while acceptance must objectively communicate assent through an authorized method, subject to...View definition . For construction, document which activities are affected and what assumptions support the revised schedule.
Who Must Approve a Change Order?
The required signatures depend on the governing contract. In some construction arrangements, the owner, contractor, and architect all sign the relevant form. Other agreements designate an owner representative or project manager with authority to approve changes.
The AIA G701 instructions explain how that particular form is executed. Other projects may use different approval requirements.
Can Work Begin Before a Change Order Is Signed?
Sometimes, but the answerCivil LitigationCivil Litigation is the court process for resolving noncriminal disputes through pleadings, motions, discovery, settlement, trial, judgment, and possible appeal. Federal civil litigation follows the Federal Rules of Civil Procedure, while state systems...View definition depends on the contract and circumstances. Some agreements provide separate directives for urgent work or situations where pricing is not yet agreed. Others require prior written approval for any added cost.
If work must proceed, document who authorized it, what was communicated, and how price and time will be resolved. Avoid assuming an informal conversation overrides a strict written change procedure.
Change Order vs. Contract Amendment
A change order usually focuses on alterations to work, price, or schedule within an existing project. A contract amendment can modify any agreed term, including confidentialityEmployment ContractAn employment contract is an agreement defining terms of an employer-employee relationship. It can cover duties, compensation, benefits, equity, confidentiality, intellectual property, restrictive covenants, termination, severance, and dispute procedures while remaining subject to...View definition , liability, payment procedures, or the length of a business relationship.
Both can legally modify an agreement if properly approved. The practical difference is often the purpose and the process defined by the parties.
How Does a Change Order Differ From a New Contract?
Change orders normally rely on the original agreement and leave unchanged terms in force. A new contract may be more appropriate when the requested work is a separate project with materially different parties, risks, or commercial arrangements.
Ask whether the existing insurance, warranties, intellectual propertyIntellectual PropertyIntellectual property, or IP, is a group of legal rights that protect certain inventions, creative works, brands, and confidential business information. Major U.S. categories include patents, copyrights, trademarks, and trade secrets.View definition , and dispute provisions still fit the new scope. A change order should not accidentally attach unsuitable old terms to a very different assignmentAssignmentAssignment transfers a contractual right or other legal interest from an assignor to an assignee. Most rights can be assigned, but contract restrictions, personal rights, material changes to the obligor’s burden, notice, defenses,...View definition .
Change Order Example
Illustrative language only: “Change Order No. 04 modifies the Work under the Agreement dated March 1. Contractor will install two additional data outlets as described in Exhibit A. The Contract Price increases by $1,200, and the Substantial Completion Date extends by two calendar days. All other terms remain unchanged.”
A complete form would identify the parties, approval signatures, and supporting documents. The particular project may also require detailed pricing or schedule justification.
What Happens if the Parties Disagree About a Change?
Disputes may concern whether a task was within the original scope, who authorized it, or how much it should cost. Begin with the signed agreement, original drawingsPatent ApplicationA Patent Application is a filing asking the USPTO to examine an invention for patent protection. Provisional and nonprovisional applications differ in purpose, requirements, examination, timing, publication, and their relationship to later patent...View definition or specifications, requests, correspondence, and work records.
If negotiations fail, the project’s contractual framework and dispute resolutionLegal DisputeA legal dispute is a disagreement or controversy involving claimed legal rights, duties, liabilities, property, or remedies. It can be resolved through negotiation, mediation, arbitration, administrative proceedings, litigation, or settlement depending on the...View definition procedure determine the next steps. A change order process is easier to use when scope boundaries were clearly defined at the outset.
How Can a Business Track Multiple Change Orders?
Use unique numbers and a change log that records status, proposed amount, approved amount, expected schedule impact, submission date, and signatures. Keep supporting estimates and updated project documents with each entry.
Calculate the cumulative effect of all approved changes. A project with several small additions may have a much larger price increase or delay than any single form suggests.
How Do Change Orders Work for Software and Consulting?
Service teams often use a similar method for features, additional research, extra design rounds, and added integrations. The change document can tie a new deliverable to acceptance tests, a fee, and a schedule.
Align the change process with the original service agreement and any statement of work. A consulting team should specify whether added requests affect previously approved milestones.
What Is the Relationship Between Change Orders and Payment?
The parties should decide whether approved change work is invoiced immediately, at the next milestone, or with the final bill. Construction contracts may use established progress billing procedures, while smaller services projects may issue a separate invoice.
State whether retainagePayment Terms ClauseA payment terms clause explains how and when a customer pays for goods or services. Learn about Net 30, deposits, milestones, disputed invoices, and late fees.View definition , deposits, or existing payment schedules apply to the changed amount. Avoid recording an extra fee without describing when it becomes payable.
Common Change Order Mistakes
- Starting extra work before the required approval is obtained.
- Describing the change too vaguely for later verificationVerified ComplaintA verified complaint is a complaint accompanied by a sworn verification or declaration under penalty of perjury confirming specified factual allegations.View definition .
- Listing an increased price without the effect on the total.
- Ignoring schedule changes or dependent tasks.
- Using an unauthorized signatory.
- Failing to update drawings, scopes, or acceptance criteriaService AgreementA service agreement is a contract in which one party agrees to perform services for another party in exchange for payment or other consideration. It commonly covers scope, fees, deliverables, service levels, intellectual...View definition .
How Do You Review a Proposed Change Order?
Check whether the work is truly outside the original scope. Then compare the proposed price with estimates, unit rates, and market inputs where appropriate. Evaluate the schedule impact and any effect on existing warranties or other obligations.
Before approving, confirm that referenced exhibits are attached, signatures are authorized, and the revised contract value is calculated consistently with prior changes.
Can AI Help Review Change Orders?
AI-assisted document reviewLegal Document ReviewLegal document review is the structured examination of documents for relevant facts, obligations, legal risk, privilege, evidence, and required action.View definition can compare the original scope to proposed changes, extract pricing and dates, identify missing exhibits, and summarize how several change orders affect a project. It can also help prepare a list of questions for a contractor or client.
Actual costs, authorization, and schedule feasibility still need confirmation from source records and the relevant project team. An AI summary should not be treated as an approval.
Frequently Asked Questions About Change Orders
Is a change order legally binding?
It may be when it satisfies the underlying contract’s approval requirements and applicable legal rules. A proposal alone is not necessarily an approved modification.
Can a change order reduce the contract price?
Yes. It may document deleted work, credits, substitutions, or other agreed reductions as well as additions.
Does every change order extend the project deadline?
No. The parties should record the actual agreed schedule effect, including zero days when appropriate.
What if a customer requests a change verbally?
Confirm the request against the contract’s authorization procedure. Written approval may be required before work or extra charges are permitted.
Key Takeaway
A change order documents an agreed adjustment to an existing project. Define the revised scope, cost, time, and approvals before relying on it, and keep each change tied to the original contract and updated project records.